Skip to main content
Loading page, please wait…
Vaidra Logo
Vaidra

Top 7 items + smart groups

UPSC GPT
New
Mains Evaluator
Test Generator
Geography Lab
New
History Lab
New
Current Affairs
Daily Solutions
Daily Puzzle

Version 2.0.0 • Built with ❤️ for UPSC aspirants

UPSC Civil Engineering PYQs 2020 | Vaidra | Vaidra
  1. Home
  2. Practice
  3. PYQs
  4. Civil Engineering
  5. 2020

Civil Engineering UPSC PYQ 2020

57 questions from the UPSC 2020 examination. Showing a preview of 3 below — generate a full practice test to solve the rest.

3 questions

1Medium
The table given below shows a project's activities along with starting and finishing time and the budgeted cost. The conditions of contract allow measurements to be made monthly and payment of the amount certified less 5% retention to be paid to the contractor after a month of submission of bills. The first bill will be submitted after a month and subsequently every month. The retention amount is to be released after 6 months of completion of the project. The annual interest rate is 15% on locked-up capital. Calculate the total profit of the contractor if he earns 10% profit on the quoted cost. Activity A: starting month 0, duration 2 months, cost Rs 4.5 lakh/month; B: starting month 1, duration 3 months, Rs 4 lakh/month; C: starting month 3, duration 1.5 months, Rs 12 lakh/month; D: starting month 3, duration 1 month, Rs 15 lakh/month; E: starting month 3.5, duration 1.5 months, Rs 4 lakh/month; F: starting month 5, duration 1 month, Rs 20 lakh/month. All activities are independent.
2Medium
Design a full penetration butt weld to connect a 16 mm thick bracket plate perpendicular to the flange of a column. A factored load of 230 kN is applied to the bracket at a distance of 350 mm from the flange of the column. Field welds and steel of grade Fe 250 were used. Also give a neat sketch of the connection. Use limit state procedure.
3Medium
Enumerate various types of track junctions. Calculate all the elements required to set out a 1 in 12 turnout taking off from a straight BG track with its curve starting from the toe of the switch, i.e., tangential to the gauge face of the outer main rail and passing through the theoretical nose of crossing (TNC). The heel divergence is given as 11.4 cm.

54 more Civil Engineering 2020 questions await

Generate a full-length practice test on Civil Engineering — pick the exact year, topic or chapter you want, and solve as many questions as you like with instant scoring and explanations.

Generate a Civil Engineering Test
Civil Engineering — All Years|All Subjects