Key Developments in the Great Nicobar Forest‑Rights Litigation
The Calcutta High Court has postponed the final hearing on a batch of petitions that challenge the diversion of forest land for the Union government’s ₹92,000 crore Great Nicobar Island (GNI) project. The new date is 13 January 2027. The delay follows the Centre’s request for additional time to file an affidavit and supporting documents on tribal rights.
Key Developments
- The Centre argues that the Protection of Aboriginal Tribes Regulations, 1956 are already in force.
- Petitioners counter that the A&NI administration issued a certificate stating that FRA rights have been settled, and this certificate is now being challenged.
- The ASG Vikramjit Banerjee sought to raise fresh preliminary objections on the maintainability of two petitions that seek to reduce buffer zones of two National Parks on Great Nicobar.
- The Attorney General R. Venkatramani also appeared before the bench.
- The Centre wants two of the petitions to be heard by the NGT or the Supreme Court, but petitioners argue they pertain to buffer‑zone reductions and must stay in the High Court.
Important Facts
• The GNI project involves diverting 121 sq.km of forest land.
• The High Court gave the Centre ten days to file its affidavit and documents, and the petitioners until the December winter break to file a rejoinder.
• A separate petition focusing solely on tribal rights and FRA compliance is scheduled for 13 January 2027, with the Attorney General’s submissions slated for 22 January 2027.
Exam Relevance
Understanding this case helps aspirants grasp:
- The interaction between central‑government projects and environmental/tribal protection laws (GS2: Polity, GS3: Environment).
- The procedural aspects of judicial review, including maintainability, jurisdiction of the High Court versus the NGT and Supreme Court.
- The significance of the