Overview
The state of Karnataka has approached the Supreme Court for a temporary injunction against Tamil Nadu and the Union government. The request concerns the CVG Link and related works that aim to utilise surplus Cauvery waters flowing down from Karnataka.
Key Developments (as of 20 Nov 2026)
- Karnataka filed a fresh injunction petition on 20 Nov 2026, alleging that Tamil Nadu proceeded with Phase‑I works without the Union’s in‑principle approval.
- The petition cites a Madras High Court order that extracted a status report showing work on the first phase began on 21 Jan 2021.
- Karnataka claims several Phase‑I structures are already completed and land has been acquired, but argues the works are illegal without Union clearance.
- The state urges the court to stop Tamil Nadu from executing the Cauvery–South Vellar Link Project and any further phases (Phase‑II, Phase‑III).
- Karnataka also seeks a directive to prevent the Union from granting the January 2021 in‑principle approval and from declaring the CVG Link a national project.
- The petition asks for demolition of the works already completed in Phase‑I.
Important Facts
• Tamil Nadu has been drawing water for the project from the surplus at Mettur Dam, estimated at about 8.60 TMC at 50 % dependability.
• Karnataka warns that unilateral utilisation of surplus water could be used by Tamil Nadu to claim future equities, harming Karnataka’s rights under the Cauvery water‑sharing agreement.
• The earlier Supreme Court order in January 2025 held that the Centre had not given in‑principle approval, so no interim relief was required then.
Exam Relevance
The case illustrates several themes that frequently appear in the UPSC syllabus:
- Inter‑state water disputes – Understanding the legal and constitutional framework governing river water sharing (GS2).
- Role of the judiciary – How the Supreme Court and High Courts intervene in federal disputes (GS2).
- Centre‑State relations – The need for Union approval for large‑scale inter‑state projects and the concept of a “national project” (GS2).
- Water‑resource management – The technical aspects of linking rivers, surplus utilisation, and the importance of dams like Mettur Dam (GS3).
Way Forward
The Supreme Court is scheduled to hear the matter on 10 Dec 2026. Possible outcomes include:
- Granting a temporary stay on all CVG Link works until the Union gives formal approval.
- Directing the Union to consider the request for “national project” status, which could streamline funding but also raise further inter‑state concerns.
- Ordering demolition of Phase‑I structures if found illegal, setting a precedent for future inter‑state projects.
For UPSC aspirants, tracking this case helps understand how water‑sharing disputes evolve from technical proposals to constitutional battles, and how the judiciary balances federalism with developmental needs.