The PAC on 19 Nov 2026 sharply rebuked the MoEFCC for failing to implement the Green India Mission (GIM). The audit by the CAG shows that only 5.3 % of the approved area is under green cover, seven years after the 2018 deadline.
Key Developments
- PAC, chaired by K.C. Venugopal, demanded a fresh time‑frame for GIM implementation.
- The 2021 revision of GIM still lacks updated guidelines from the Ministry.
- Venugopal called the mission a “complete failure” and highlighted the missing Aravalli green wall.
Important Facts
• The original Cabinet approval (Feb 2014) earmarked ₹13,000 crore for 2.8 million hectares. • By March 2025, only 0.148 million hectares were planted – a 5.3 % achievement. • Of the total outlay, ₹10,600 crore was to come from CAMPA, MGNREGS and the National Afforestation Programme, but none was released.
A study by the IISc found no change in 70 % of surveyed sites and only 10 % showed any tree cover. Saplings were often planted in inappropriate locations such as existing forests or paddy fields, while degraded lands like scrublands and old mines were ignored.
The mission’s own budget of ₹2,400 crore for four years yielded only ₹1,149 crore over a decade. The Governing Council met merely twice in ten years, breaching the stipulated annual meeting rule. No annual report, social audit (in 14 of 16 states), or carbon‑sequestration measurement was undertaken. In 39 % of sampled villages, no implementation plan existed, and in over half the cases the Gram Sabha never approved the plan.
Exam Relevance
Understanding the GIM failure illustrates challenges in policy implementation, inter‑agency coordination, and fund disbursement—core topics for GS III (Environment & Climate Change) and GS II (Governance & Public Administration). The role of oversight bodies like the PAC and the audit function of the CAG are frequent UPSC questions. The case also highlights the importance of participatory mechanisms such as the Gram Sabha in rural development programmes.
Way Forward
- Issue revised GIM guidelines with clear, time‑bound targets.
- Ensure full release of earmarked funds from CAMPA, MGNREGS and NAP.
- Conduct annual social audits and publish transparent progress reports.
- Involve Gram Sabhas in plan preparation and approval.
- Measure carbon sequestration to assess climate‑impact benefits.
Timely corrective action will not only revive the mission’s original ambition but also strengthen India’s commitment to international climate goals.