Skip to main content
Loading page, please wait…
HomeCurrent AffairsEditorialsGovt SchemesLearning ResourcesUPSC SyllabusPricingAboutBest UPSC AIUPSC AI ToolAI for UPSCUPSC ChatGPT

© 2026 Vaidra. All rights reserved.

PrivacyTerms
Vaidra Logo
Vaidra

Top 4 items + smart groups

UPSC GPT
New
Current Affairs
Daily Solutions
Daily Puzzle
Mains Evaluator

Version 2.0.0 • Built with ❤️ for UPSC aspirants

Nearly 4 GW of solar capacity in Rajasthan hit by transmission constraints

Nearly 4 GW of solar capacity in Rajasthan hit by transmission constraints
Approximately 4,300 MW of solar power capacity in Rajasthan faces daytime curtailment due to inadequate transmission infrastructure, jeopardizing projects worth ₹20,000 crore; industry representatives are urging the government to consider short-term relief measures to prevent a complete shutdown and stranded assets. This situation highlights the critical need for synchronized development of renewable energy generation and transmission infrastructure for India's energy transition.
Overview Nearly 4,300 MW of solar power capacity in Rajasthan is facing complete daytime curtailment due to inadequate transmission infrastructure. This situation puts projects worth approximately ₹20,000 crore at risk, according to industry sources. The issue highlights the critical need for synchronized development of renewable energy generation and transmission infrastructure. Key Developments Projects Affected A total of 26 solar projects, developed by companies including Adani , ReNew , Serentica , Juniper , Zelestra , ACME , and Amp Energy , are currently supplying power under the Temporary General Network Access (T-GNA) framework. These projects' associated transmission systems are yet to be commissioned, leading to curtailment. Transmission Capacity Constraints According to data from the Northern Regional Load Despatch Centre (NRLDC) , Rajasthan has around 23 GW of commissioned renewable energy capacity. However, transmission capacity stands at about 18.9 GW . The entire transmission capacity has been allocated to projects with long-term General Network Access (GNA) , leaving over 4 GW of capacity operating under T-GNA without evacuation capability. Impact of New Transmission Line Despite the commissioning of the 765 kV Khetri-Narela transmission line, only about 600 MW of additional transmission capacity became available. Simultaneously, over 4,300 MW was operationalized under long-term GNA , effectively exhausting surplus margins. NRLDC Action In an email dated December 11 , NRLDC withdrew the No Objection Certificates (NOC) for the 26 projects following the commissioning of the line and operationalization of long-term GNA . Industry Concerns and Recommendations Project Viability Developers warned that prolonged curtailment could severely impact project viability and debt servicing. They flagged the issue as a growing systemic risk as generation capacity continues to outpace transmission additions in renewable-rich States such as Rajasthan . Proposed Solutions Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme (SPS) to improve evacuation under T-GNA . They also called for the dynamic reallocation of unused GNA margins to T-GNA projects during low utilization periods. The use of Dynamic Line Rating (DLR) to maximize real-time transmission capacity and prevent renewable assets from turning stranded was also suggested. Industry Perspective An industry official stated that most of the 4.3 GW capacity is well within its notified connectivity start date. However, due to delay in commissioning of their Associated Transmission System (ATS) , they are forced to deliver power under T-GNA . Government's Stance and Challenges The government had earlier indicated that commissioning of the 765 kV Khetri-Narela transmission line would significantly reduce 55% peak hour curtailment faced by Renewable Energy (RE) generators operating under the T-GNA arrangement. However, the actual capacity addition has been much lower than anticipated. Proposed Measures to Avoid Stranded Capacity To avoid stranded capacity, the industry has proposed that a T-GNA -only approach can be adopted for all future RE capacity additions in Rajasthan until evacuation margins are demonstrably available. UPSC Relevance This issue is relevant to GS3 (Infrastructure, Energy) and GS2 (Government Policies) . It highlights the challenges in integrating renewable energy into the grid and the need for effective policy and infrastructure planning. Key Takeaways The mismatch between renewable energy generation and transmission capacity is a significant challenge. Effective coordination between generation and transmission projects is crucial. Innovative solutions like DLR and SPS can improve grid utilization. Policy interventions are needed to ensure the viability of renewable energy projects.
Loading article...

Quick Reference

Key Insight

Transmission bottlenecks threaten Rajasthan's solar expansion and renewable targets.

Key Facts

  1. Nearly 4,300 MW of solar capacity in Rajasthan faces daytime curtailment due to inadequate transmission.
  2. Projects worth approximately ₹20,000 crore are at risk of becoming stranded assets.
  3. 26 solar projects (including Adani, ReNew, Serentica) operate under Temporary General Network Access (T‑GNA).
  4. Rajasthan has ~23 GW commissioned renewable capacity but only ~18.9 GW transmission capacity.
  5. The 765 kV Khetri‑Narela line added just ~600 MW of usable transmission, far short of the gap.
  6. NRLDC withdrew No‑Objection Certificates for the 26 projects in an email dated Dec 11 (2025).
  7. Industry proposes Special Protection Scheme, Dynamic Line Rating, and reallocation of GNA margins as short‑term relief.

Background

India's renewable‑energy push has outpaced grid expansion, creating a generation‑transmission mismatch that hampers meeting the 450 GW renewable target by 2030. Rajasthan, a solar‑rich state, exemplifies the governance challenge of synchronising infrastructure projects, financial viability of developers, and policy implementation.

UPSC Syllabus

  • GS3 — Infrastructure - Energy, Ports, Roads, Airports, Railways
  • Essay — Economy, Development and Inequality
  • Prelims_GS — Environmental Issues and Climate Change
  • Essay — Environment and Sustainability

Mains Angle

GS III (Infrastructure & Energy) – Discuss the challenges of integrating large‑scale renewable generation with existing transmission networks and evaluate policy measures to prevent curtailment and stranded assets.

Explore:Current Affairs·Editorial Analysis·Govt Schemes·Study Materials·Previous Year Questions·UPSC GPT
  1. Home
  2. Prepare
  3. Current Affairs
  4. Nearly 4 GW of solar capacity in Rajasthan hit by transmission constraints
Login to bookmark articles
Login to mark articles as complete

Overview

gs.gs375% UPSC Relevance

Full Article

Overview

Nearly 4,300 MW of solar power capacity in Rajasthan is facing complete daytime curtailment due to inadequate transmission infrastructure. This situation puts projects worth approximately ₹20,000 crore at risk, according to industry sources. The issue highlights the critical need for synchronized development of renewable energy generation and transmission infrastructure.

Key Developments

Projects Affected

  • A total of 26 solar projects, developed by companies including Adani, ReNew, Serentica, Juniper, Zelestra, ACME, and Amp Energy, are currently supplying power under the Temporary General Network Access (T-GNA) framework.
  • These projects' associated transmission systems are yet to be commissioned, leading to curtailment.

Transmission Capacity Constraints

  • According to data from the Northern Regional Load Despatch Centre (NRLDC), Rajasthan has around 23 GW of commissioned renewable energy capacity.
  • However, transmission capacity stands at about 18.9 GW.
  • The entire transmission capacity has been allocated to projects with long-term General Network Access (GNA), leaving over 4 GW of capacity operating under T-GNA without evacuation capability.

Impact of New Transmission Line

  • Despite the commissioning of the 765 kV Khetri-Narela transmission line, only about 600 MW of additional transmission capacity became available.
  • Simultaneously, over 4,300 MW was operationalized under long-term GNA, effectively exhausting surplus margins.

NRLDC Action

  • In an email dated December 11, NRLDC withdrew the No Objection Certificates (NOC) for the 26 projects following the commissioning of the line and operationalization of long-term GNA.

Industry Concerns and Recommendations

Project Viability

Developers warned that prolonged curtailment could severely impact project viability and debt servicing. They flagged the issue as a growing systemic risk as generation capacity continues to outpace transmission additions in renewable-rich States such as Rajasthan.

Proposed Solutions

  • Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme (SPS) to improve evacuation under T-GNA.
  • They also called for the dynamic reallocation of unused GNA margins to T-GNA projects during low utilization periods.
  • The use of Dynamic Line Rating (DLR) to maximize real-time transmission capacity and prevent renewable assets from turning stranded was also suggested.

Industry Perspective

An industry official stated that most of the 4.3 GW capacity is well within its notified connectivity start date. However, due to delay in commissioning of their Associated Transmission System (ATS), they are forced to deliver power under T-GNA.

Government's Stance and Challenges

The government had earlier indicated that commissioning of the 765 kV Khetri-Narela transmission line would significantly reduce 55% peak hour curtailment faced by Renewable Energy (RE) generators operating under the T-GNA arrangement. However, the actual capacity addition has been much lower than anticipated.

Proposed Measures to Avoid Stranded Capacity

To avoid stranded capacity, the industry has proposed that a T-GNA-only approach can be adopted for all future RE capacity additions in Rajasthan until evacuation margins are demonstrably available.

UPSC Relevance

This issue is relevant to GS3 (Infrastructure, Energy) and GS2 (Government Policies). It highlights the challenges in integrating renewable energy into the grid and the need for effective policy and infrastructure planning.

Key Takeaways

  • The mismatch between renewable energy generation and transmission capacity is a significant challenge.
  • Effective coordination between generation and transmission projects is crucial.
  • Innovative solutions like DLR and SPS can improve grid utilization.
  • Policy interventions are needed to ensure the viability of renewable energy projects.
Read Original

Transmission bottlenecks threaten Rajasthan's solar expansion and renewable targets.

Key Facts

  1. Nearly 4,300 MW of solar capacity in Rajasthan faces daytime curtailment due to inadequate transmission.
  2. Projects worth approximately ₹20,000 crore are at risk of becoming stranded assets.
  3. 26 solar projects (including Adani, ReNew, Serentica) operate under Temporary General Network Access (T‑GNA).
  4. Rajasthan has ~23 GW commissioned renewable capacity but only ~18.9 GW transmission capacity.
  5. The 765 kV Khetri‑Narela line added just ~600 MW of usable transmission, far short of the gap.
  6. NRLDC withdrew No‑Objection Certificates for the 26 projects in an email dated Dec 11 (2025).
  7. Industry proposes Special Protection Scheme, Dynamic Line Rating, and reallocation of GNA margins as short‑term relief.

Background & Context

India's renewable‑energy push has outpaced grid expansion, creating a generation‑transmission mismatch that hampers meeting the 450 GW renewable target by 2030. Rajasthan, a solar‑rich state, exemplifies the governance challenge of synchronising infrastructure projects, financial viability of developers, and policy implementation.

UPSC Syllabus Connections

GS3•Infrastructure - Energy, Ports, Roads, Airports, RailwaysEssay•Economy, Development and InequalityPrelims_GS•Environmental Issues and Climate ChangeEssay•Environment and Sustainability

Mains Answer Angle

GS III (Infrastructure & Energy) – Discuss the challenges of integrating large‑scale renewable generation with existing transmission networks and evaluate policy measures to prevent curtailment and stranded assets.

Analysis

Prelims Facts (Factual Knowledge)

  1. Rajasthan's total commissioned renewable energy capacity is approximately 23 GW.
  2. Transmission capacity in Rajasthan is about 18.9 GW.
  3. The Khetri-Narela transmission line added only 600 MW of capacity.
  4. 26 solar projects are affected by the curtailment.
  5. The curtailment impacts approximately 4,300 MW of solar power.
  6. NRLDC withdrew NOCs on December 11.

Mains Angles (Analytical Discussion)

  1. Analyze the challenges in renewable energy transmission infrastructure in India, particularly in states like Rajasthan.
  2. Discuss the impact of transmission constraints on the viability of renewable energy projects and potential solutions.
  3. Evaluate the role of technologies like Dynamic Line Rating (DLR) and Special Protection Schemes (SPS) in improving grid utilization.
  4. Assess the policy and regulatory framework for granting transmission access to renewable energy projects (GNA vs. T-GNA).
  5. What are the implications of curtailment of renewable energy on India's climate goals and energy security?

Essay Themes (Critical Thinking)

Renewable Energy Transition: Challenges and Opportunities

Infrastructure Development for Sustainable Growth

Energy Security and Grid Modernization in India

Practice Questions

GS1
Easy
Prelims MCQ

Renewable Energy – Transmission Constraints

1 marks
4 keywords
GS3
Medium
Mains Short Answer

Energy Policy – Grid Management

5 marks
4 keywords
GS3
Hard
Mains Essay

Infrastructure Planning & Energy Governance

20 marks
5 keywords
Related:Daily•Weekly

Loading related articles...

Loading related articles...

Tip: Click articles above to read more from the same date, or use the back button to see all articles.

Nearly 4 GW of solar capacity in Rajasthan... | UPSC Current Affairs

Related Topics

  • 📚Subject TopicIndia Emerges as Third-Largest Solar Power Producer in 2023
  • 📚Subject TopicArtesian Well in Rajasthan and Tethys Sea
  • 📚Subject TopicBalancing Energy Transition & Security
  • 📰Current AffairsSupreme Court Rules Rajasthan District Milk Unions Independent, Outside Writ Jurisdiction (2026)
  • 📰Current AffairsIMD Issues Heatwave to Severe Heatwave Alerts Across Gujarat, Rajasthan, Delhi and Other Regions – March 11, 2026